My Aim to Provide you quality contents, Tips & Tricks, Software, Microsoft Office, Graphic Editing (Adobe PhotoShop, After Affects, Illustrator, inDesign) Corel Draw, Corel Video Studio, Cyberlink PowerDirector, Power ActionCinema, Tutorials about Blogging and VU Assignments, Quizes & GDB Solutions and Much More... at regular Basis
                                     ***    Kindly Subscribe our Official YouTube Channel "INFOPALACESS OFFICIAL-Tuts: in this channel we upload Programming (C,C++,C# JAVA, PHP), Web Development, Graphics Editing and Microsoft Office Step by Step Tutorials from bigginer to Advance Level. We also provide free online courses at our YouTube Channel. ***   Graded Assignments/Quizes and GDB will start in Next Week. Solution ideas of All assignments, Quizes and GDB will be available here. If you have any problem regarding this then you can contact us.

MTH601 Assignment 1 Solution Spring 2019 Step by Step Guide (VU Assignment)

 Info!  Please Don't Make 100% copy of your assignment Solution. Make some changes so that your solution look differrent than other students. If you make Exact copy of then you can get marks zero.

Solution of MTH601 Assignment No 1 2019 Operations Research Due Date 19-05-2019

Solution of Assignment is Given Below;

Watch the Video to know that how i solve this assignment with step by step guide. If you want to download Solution File in Ms Word File Scroll downl and go to Download Button



Question:   For the given network diagram

1. Construct a table which shows the relationship between the activities and their predecessors.

2. Calculate the following time estimates for each activity.
 Earliest Start Time(EST)
 Earliest Finish Time (EFT)
 Latest Start Time (LST)
 Latest Finish Time (LFT)

3. Calculate the total float for each activity.

4. Identify the critical path.

5. Find the project completion time.

Note: The duration of each given activity is in days

Download Assignment File by

Solution:

1. Construct the table which shows the relationship.

Activities Predecessor
A -
B A
C -
D C
E B
F D, E
G F


2. Calculate the following

a. Earliest Start Time
b. Earliest Finish Time
c. Latest Start Time
d. Latest Finish Time

ActivitiesEarliest Start TimeEarliest Finish TimeLatest Start TimeLatest Finish Time
A0404
B411411
C06612
D6111318
E11181118
F18241824
G24292429

4. Critical Path

There are 2 Paths

A+B+E+F+G = 4 +7 + 7 +6+5 = 29
C+D+F+G=6+5+6+5 =22

A+B+E+F+G longest Path hence critical path is 29.

5. Project Completion Time is 29 Days


How to Make Changes and Submit file

You need to submit your assignment in doc or docx. Make necessary changes (Like your VU ID, Name, Degree Name) before submission.To make Changes in the file Just watch the video Given above to get step by step guide.


How to Download File

To Download File follow these steps

  • Click on Download Button below in Red Color

  • A pop up window will appear Close the popup window and come back to this page and again click on Download Button.

  • Now you will go to another page in same open tab Wait for 5-6 seconds then click on Skip this Ad at top right Corner. (If again any popup window will appear then close the pop up windows and stay at same tab).

  • In next again you may see another ad again follow the Step 2.

  • That's It you have done it Now download file will come to you.






If you have any Problem regarding your assignment Solution then you can contact Us or leave a Comment below. You can also subscribe our Official YouTube Channel to get guided videos of all assignments, quizes or GDB. You can also join our Official WhatsApp Groups by Click on the links Below.

DescriptionLinks
YouTube Channel:Infopalacess Official Tuts
WhatsApp Group 1:VU Assignments Portal by Infopalacess 2
WhatsApp Group 2VU Assignments Portal by Infopalacess 2
WhatsApp Group 23- VU Solutions by Infopalacess

Post a Comment

0 Comments