For the given network diagram
1. Construct a table which shows the relationship between the activities and their predecessors.
2. Calculate the following time estimates for each activity.
Earliest Start Time(EST)
Earliest Finish Time (EFT)
Latest Start Time (LST)
Latest Finish Time (LFT)
3. Calculate the total float for each activity.
4. Identify the critical path.
5. Find the project completion time.
Note: The duration of each given activity is in days
Download Assignment File by
1. Construct the table which shows the relationship.
Activities | Predecessor |
---|---|
A | - |
B | A |
C | - |
D | C |
E | B |
F | D, E |
G | F |
2. Calculate the following
a. Earliest Start Time
b. Earliest Finish Time
c. Latest Start Time
d. Latest Finish Time
Activities | Earliest Start Time | Earliest Finish Time | Latest Start Time | Latest Finish Time |
---|---|---|---|---|
A | 0 | 4 | 0 | 4 |
B | 4 | 11 | 4 | 11 |
C | 0 | 6 | 6 | 12 |
D | 6 | 11 | 13 | 18 |
E | 11 | 18 | 11 | 18 |
F | 18 | 24 | 18 | 24 |
G | 24 | 29 | 24 | 29 |
4. Critical Path
There are 2 Paths
A+B+E+F+G = 4 +7 + 7 +6+5 = 29
C+D+F+G=6+5+6+5 =22
A+B+E+F+G longest Path hence critical path is 29.
5. Project Completion Time is 29 Days
How to Make Changes and Submit file
You need to submit your assignment in doc or docx. Make necessary changes (Like your VU ID, Name, Degree Name) before submission.To make Changes in the file Just watch the video Given above to get step by step guide.
How to Download File
To Download File follow these steps
- Click on Download Button below in Red Color
- A pop up window will appear Close the popup window and come back to this page and again click on Download Button.
- Now you will go to another page in same open tab Wait for 5-6 seconds then click on Skip this Ad at top right Corner. (If again any popup window will appear then close the pop up windows and stay at same tab).
- In next again you may see another ad again follow the Step 2.
- That's It you have done it Now download file will come to you.
If you have any Problem regarding your assignment Solution then you can contact Us or leave a Comment below. You can also subscribe our Official YouTube Channel to get guided videos of all assignments, quizes or GDB. You can also join our Official WhatsApp Groups by Click on the links Below.
Description | Links |
---|---|
YouTube Channel: | Infopalacess Official Tuts |
WhatsApp Group 1: | VU Assignments Portal by Infopalacess 2 |
WhatsApp Group 2 | VU Assignments Portal by Infopalacess 2 |
WhatsApp Group 2 | 3- VU Solutions by Infopalacess |
0 Comments